Province | Subbasin | % |
---|---|---|
Upper Snake | Snake Headwaters | 100.00% |
Previous: | Next: |
---|---|
46273 REL 21: 2010-076-00 EXP NOAA- SNAKE R SOCKEYE MIGRATION/SURV STUDIES |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Produce Environmental Compliance Documentation | A: 165. Produce Environmental Compliance Documentation | 02/28/2013 | 02/28/2013 | |
Implant radio transmitters and PIT tags in Snake River sockeye salmon | B: 158. Implant radio transmitters | 05/20/2012 | 04/12/2012 | |
Install, maintain, and remove temporary fixed-site radio telemetry monitoring stations | C: 70. Install, maintain, and remove temporary fixed-site radio telemetry monitoring stations | 09/30/2012 | 09/30/2012 | |
PIT & Radio tagged Juvenile sockeye salmon data | D: 157. Monitor detections at fixed site radio telemetry monitoring station | 10/31/2012 | 10/31/2012 | |
Analyze and interpret radio telemetry and PIT tag detection data | E: 162. Analyze and interpret radio telemetry and PIT tag detection data | 10/31/2012 | 10/31/2012 | |
Attach FY 12 Progress Report in Pisces | F: 132. Submit Progress Report for the period (Mar 2012) to (Feb 2013) | 02/28/2013 | 01/28/2013 | |
Funding Package - Submit draft to COTR | G: 119. Project management, scheduling, and agency coordination. | 11/30/2012 | 11/30/2012 |
Primary Focal Species | Work Statement Elements |
---|---|
Sockeye (O. nerka) - Snake River ESU (Endangered) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Produce Environmental Compliance Documentation | 03/01/2012 | ||||||
B | 158 | Implant radio transmitters | 03/01/2012 | ||||||
C | 70 | Install, maintain, and remove temporary fixed-site radio telemetry monitoring stations | |||||||
D | 157 | Monitor detections at fixed site radio telemetry monitoring station | 03/01/2012 | ||||||
E | 162 | Analyze and interpret radio telemetry and PIT tag detection data | 03/01/2012 | ||||||
F | 132 | Submit Progress Report for the period (Mar 2012) to (Feb 2013) | 03/01/2012 | ||||||
G | 119 | Project management, scheduling, and agency coordination. | 03/01/2012 | ||||||
H | 185 | Periodic Status Reports for BPA | 03/01/2012 |